| Project Expansions & Extensions (subject to change) | Year To Be Done | Fiscal Year 2004 | Fiscal Year 2005 | Fiscal Year 2006 | Fiscal Year 2007 | Fiscal Year 2008 | | Hickory Ridge Rd. | 1 | Done | | | | | | Palmer Rd. | 1 | In Progress | | | | | | Maple Hill Rd. | 1 | In Progress | | | | | | Alhambra Dr. | 2 | | X | | | | | Horn Springs Rd. | 2 | | X | | | | | I-40 Crossing 231 S. | 2 | | X | | | | | Deer Park | 3 | | | X | | | | Eastland & Hillakes | 3 | | | X | | | | Holloway Dr. | 3 | | | X | | | | Martha Leeville Rd. | 3 | | | X | | | | Thorn Dr. & Court | 3 | | | X | | | | Bluegrass Pkwy. | 4 | | | | X | | | Coles Ferry Pk. | 4 | | | | X | | | Murfreesboro Rd. | 5 | | | | | X |
Five Year Plan is subject to change at budget time each year Any changes will be posted here.
|
|
|